How can past labor time sheets and invoices help future AV job estimates?

  1. By providing a reference for material costs

  2. By showcasing employee performance

  3. By analyzing past costs for labor and shipping

  4. By demonstrating customer satisfaction

The correct answer is: By analyzing past costs for labor and shipping

Using past labor time sheets and invoices can significantly enhance the accuracy of future AV job estimates through the analysis of historical costs associated with labor and shipping. This information acts as a benchmark, allowing professionals to evaluate how much time has typically been allocated to similar jobs and the associated costs incurred. When analyzing past labor data, one can identify trends in productivity, which can inform decisions about staffing needs for future projects. Moreover, by reviewing invoices, estimates can factor in shipping costs that may vary based on the project's scale or location. Together, these insights result in more precise estimations, budgeting, and planning for upcoming projects, ultimately leading to better resource allocation and financial management for the AV jobs.